We have moved!
October 8, 2006 by Kenneth Carlson, MD
Yes, the day has finally come! We are now located at 891 23rd Street NE, Salem. Our building is at the intersection of 23rd street and D street. 23rd Street intersects with D street about halfway between Lancaster St and Downtown. Closest large cross streets would be between Hawthorne and 17th. Click read more for area map and driving directions.
We are still settling in so excuse our mess but we are now up to full schedules as of Saturday October 6th. Pictures documenting our move are now available in the photo
gallery. We hope to add more in the near future as we collect pictures from everyone’s cameras so check back soon. Read more
Moving Day!
September 20, 2006 by Kenneth Carlson, MD
We are proud to announce that we are moving October 6th to our new building. Unfortunately we will be closed for that weekend beginning noon on Friday (10/6) until Monday AM when we open at our usual 0800. We are hoping to possibly open on Saturday AM but can’t guarantee at this time due to the uncertainties of getting a new building ready for quality patient care.
As always we will have physicians and nurses on call for urgent questions during this time. We apologize in advance for the reduced availability that weekend but we hope that this will only happen every 29 years (as long as Childhood Health has been in Salem). We look forward to serving your family’s healthcare needs in our new space!
Check out our building update page for maps, pictures, videos and general description of the project.
Updated building pictures
September 2, 2006 by Kenneth Carlson, MD
With only a few short weeks we would like to share some more pictures showing the progress. Paint is going on the walls, lighting is being installed and soon flooring. Check out pictures here.
Building completion
August 8, 2006 by Kenneth Carlson, MD
We are now entering the final phase of construction. Exterior planking is going on and interior walls are getting drywall. Completion is anticipated mid September with us moving first week in October. If you have an October or later appointment be sure to double check with the office as the dates get closer to make sure you go to the correct location. We will update our web site and on-hold phone message with more information as the date creeps closer. We are very excited about the big day approaching and thank all our patients and their families for their support during this transition. For an overview of the building project go here. For pictures go here.
Building is taking shape
June 27, 2006 by Kenneth Carlson, MD
Walls are up and roof construction has begun. Shape of the building is there and it is really getting exciting. Windows, ceilings, etc all coming in next few weeks. At this time we are on track for a September completion with move in soon after. Keep checking back for updates. Check out new photos.
Walls are taking shape
May 12, 2006 by Kenneth Carlson, MD
Starting to look like a building now. Walls are going up with external framing being completed this week. Second story framing to begin next week. Keep an eye on this space for updates and more pictures. Check out our photo gallery to see photos documenting the process from the beginning. For a brief description of our new building click here.
Foundation is poured
April 12, 2006 by Kenneth Carlson, MD
The foundation is taking shape on our new building. The basic outline of the building with evidence of where walls will be built can now be seen. Work continue to be generally on track for a Fall move date. Check out more pictures in our photo gallery. General description of our building project is also available under building updates.